La Glâne training centre
Avesco Rent has been chosen as a key player in the renovation of the Glâne orientation cycle.
This major project involves the creation of a temporary school designed to accommodate more than 600 pupils from August 2021.
This temporary structure will be built on the site of a former school sports field, and will stand out for its innovative and functional character.
The solution adopted for this project is characterised by the speed with which it can be put in place, while offering optimum comfort for pupils.
It is based on the assembly of 246 containers carefully fitted out to meet educational needs.
These containers will house no fewer than 27 classrooms, equipped with all the necessary amenities, as well as changing rooms and staircases to facilitate movement.
The temporary school will be operational for a period of 36 months, allowing educational activities to continue during the renovation work.
This innovative project in no way sacrifices the quality of teaching.
The interior of the classrooms will ensure a fresh atmosphere conducive to learning.
Students will also have access to areas dedicated to science and the visual arts, as well as preparatory rooms.
To encourage interaction and educational innovation, some classrooms will be equipped with connected tablets and interactive whiteboards.
This modern equipment can then be reinstalled in the new school building once the renovation work is complete.
Avesco Rent is proud to contribute to improving the educational environment in Glâne by offering a temporary solution that is both practical and inspiring for pupils and teachers.
We are convinced that this initiative will help preserve the quality of teaching during the transition period to the new orientation cycle, thereby ensuring a promising future for the region’s learners.
Goal
As part of the renovation of the Glâne training centre, a temporary school will host more than 600 students. This building, located on an old sports field, will consist of 246 shipping containers and will contain 27 classrooms, as well as changing rooms and stairways for a period of 36 months. Our temporary solution combines speed and comfort for students. In fact, fresh air will be guaranteed inside the classrooms and students will also have science laboratories, visual arts and exam rooms. Some classrooms will even be equipped with connected tablets and interactive whiteboards which will then be moved to the new school building.
Material
246 containers which include classrooms, changing rooms, stairs, science laboratories, visual arts and exam rooms.
Duration
The temporary school will be present for a period of 36 months. Delivery of the project is scheduled for August 2021.